1000 hours! Countdown till the opening of Section 2, The Crossover "White" trail

JR Zano

Member
So people have been asking me "how long" will it take to build the next section of the Crossover "White" trail. Well I thought about it, consulted with Art, and a 1000 hours is my best guess.
So how long will it take, well that is up to the volunteer turn out. For example, if we get 10 volunteers every work day, and we work 5 hours each day, and 2 days a month, well then it will take about 10 months. But, if we had 50 volunteers, working 5 hours each day 2 days a month, well then it would take about 2 months. But we can't work when there is snow on the ground or its frozen, so how long???? I have no idea.
Countdown, I am going to post the hours worked at each session so this way you guys can keep track of the progress we are making. Also this my help motivate people to help, and help all of us get this done so we can ride it.

See you on the trails
James
 

greeek32

Active Member
Hey James, great riding with you guys yesterday. I'm gonna try and get out for TM more depending on my work load in the fall.

-Ted
 

JR Zano

Member
967 hours to go.

Sunday 8/10 was our first day of construction on this section. I would like to thank,

Art
Ellen
James
Cameron
Scott
Kevin
Bill
Mark
Manny

For putting in 33 hours of work. Great job guys.

10583975_10204366153384271_4611079331811882733_n.jpg


10374969_10204366153424272_7655851272017794000_n.jpg
 
Last edited:

pixychick

JORBA: Ringwood
JORBA.ORG
I forgot to write down one volunteer, so make that 967 hours!!

Thanks volunteers!, You guys and gals did some great work yesterday. I am impressed with how much got done. :D
 

pixychick

JORBA: Ringwood
JORBA.ORG
Just want to remind everyone that we are back on this week for trail work:

Dirty Thursday (Aug 21) 4:00 pm

Saturday (Aug 23) at 9:00 am

Both will meet in Lot C and be prepared to ride your bike to the work site. It is a few miles in from the lot.

This will be Ringwood's last race paydirt for 2014. However we may have a few more dates later in the fall. :)
 

JR Zano

Member
940 hours to go.

Thursday 8/21 I would like to thank,

Ben
David
Tom
Luke
Stef
Pete
Al
Ellen
Art

For putting in 27 hours of work. Great job guys.

10625118_10204462335948775_1156144060585443453_n.jpg

10363488_10204462335908774_6834491135747870311_n.jpg
 
Last edited:

JR Zano

Member
845 Hours to go,

Saturday 8/23, we would like to thank,

8/23:
Henry
Jon
Scott
Bill
Ben
David
Al
Mike
Frank
James
Willy
Patti
Pete
Dar
Marianne
Greg
Art
Ellen

For putting in 95 hours of work. Great job guys.

10384352_10204462335988776_3269582813066331647_n.jpg
 

JR Zano

Member
Some more work days have been added:

Saturday Sep 20 9:00 am Lot C

Sunday Sep 28 9:00 am Lot C

Come out and see what we are working on....
 

Trail Conditions

Current Conditions

powered by Trailforks.com